πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Kincardine Grid Services Complex - Energy Storage Facility

N/O Kincardine Substation, Kincardine, Alloa, Clackmannanshire, FK10 4BJ

Kincardine Grid Services Complex - Energy Storage Facility is a 400 MW battery storage project in Scotland. The applicant or operator on record is Amp Energy. Planning permission has been granted as of January 2022 and it is awaiting construction. The determining authority is Sco…

Consented / Approved
Project stageConsented
  1. PlanningAug 2021 (completed)
  2. ConsentedJan 2022 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2022-06-08.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

400.000 MW
Power Capacity

πŸ“‹ Project Overview

Kincardine Grid Services Complex - Energy Storage Facility is a 400 MW battery storage project in Scotland. The applicant or operator on record is Amp Energy. Planning permission has been granted as of January 2022 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00003326.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)400.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAmp Energy
Owner / operatorAmp Energy
Year consented2022
LocationN/O Kincardine Substation, Kincardine, Alloa, Clackmannanshire, FK10 4BJ
RegionScotland
Coordinates56.0729479Β°N, 3.7230508Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2021-08-19
2022-01-05