Kilmarnock Battery Energy Storage System

250 metres (m) to the north of the existing Kilmarnock South Substation, Ayrshire, KA1 5JW

Kilmarnock Battery Energy Storage System is a 500 MW battery storage project in Scotland. The applicant or operator on record is Matrix Renewables. Planning permission has been granted as of April 2025 and it is awaiting construction. The determining authority is Scottish Governm…

Consented / Approved
Project stageConsented
  1. PlanningSep 2023 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-06-15.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

500.000 MW
Power Capacity

πŸ“‹ Project Overview

Kilmarnock Battery Energy Storage System is a 500 MW battery storage project in Scotland. The applicant or operator on record is Matrix Renewables. Planning permission has been granted as of April 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004941.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)500.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperMatrix Renewables
Owner / operatorMatrix Renewables
Year consented2025
Location250 metres (m) to the north of the existing Kilmarnock South Substation, Ayrshire, KA1 5JW
RegionScotland
Coordinates55.5721268Β°N, 4.4380177Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2023-09-28