(Arecloch Phase 2) land five kilometres to the south of Barrhill, five kilometres to the northeast of New Luce and 11km to the northwest of Kirkcowan, Dumfries and Galloway
Kilgallioch wind farm is a 239 MW onshore wind project in Scotland. The applicant or operator on record is Scottish Power Renewables. It is recorded as operational since December 2017. The determining authority is Scottish Government (S36).β¦
OperationalΒ· Since 2017
Project stageOperating
PlanningMar 2010 (completed)
ConsentedFeb 2013 (completed)
ConstructionJul 2015 (completed)
OperatingDec 2017 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2018-02-22.
Registered planning capacity; not measured generation.
Kilgallioch wind farm is a 239 MW onshore wind project in Scotland. The applicant or operator on record is Scottish Power Renewables. It is recorded as operational since December 2017. The determining authority is Scottish Government (S36).
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
239.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Scottish Power Renewables
Owner / operator
Scottish Power Renewables
Year consented
2013
Construction started
2015
Commissioned / target
2017
Location
(Arecloch Phase 2) land five kilometres to the south of Barrhill, five kilometres to the northeast of New Luce and 11km to the northwest of Kirkcowan, Dumfries and Galloway