Kerriers Solar Park

Land At Kerriers Withiel Bodmin Cornwall, Cornwall

Kerriers Solar Park is a 9.6 MW solar farm project in South West. The applicant or operator on record is Kronos Solar. It is recorded as operational since September 2014. The determining authority is Cornwall, reference PA12/10939.…

Operational Β· Since 2014
Project stageOperating
  1. PlanningJan 2013 (completed)
  2. ConsentedMar 2013 (completed)
  3. ConstructionFeb 2014 (completed)
  4. OperatingSep 2014 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2015-09-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

9.600 MW
Registered Capacity
2014
Commissioned

πŸ“‹ Project Overview

Kerriers Solar Park is a 9.6 MW solar farm project in South West. The applicant or operator on record is Kronos Solar. It is recorded as operational since September 2014. The determining authority is Cornwall, reference PA12/10939.

Site Schematic

SUBSTATION ? ha Β· 9.6 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)9.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKronos Solar
Owner / operatorKronos Solar
Year consented2013
Construction started2014
Commissioned / target2014
LocationLand At Kerriers Withiel Bodmin Cornwall, Cornwall
RegionSouth West
Coordinates50.4423531Β°N, 4.8163918Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround

πŸ“… Project Timeline

2013-01-15
2013-03-15
2014-02-01
2014-09-19