Keltneyburn Hydro is a 2 MW conventional hydro project in Scotland. The applicant or operator on record is Keltneyburn Hydro Ltd. It is recorded as operational since May 2010. The determining authority is Perth and Kinross.…

Operational Β· Since 2010
Project stageOperating
  1. PlanningNov 2004 (completed)
  2. ConsentedSep 2008 (completed)
  3. Construction (completed)
  4. OperatingMay 2010 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2012-01-25.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Registered Capacity
2010
Commissioned

πŸ“‹ Project Overview

Keltneyburn Hydro is a 2 MW conventional hydro project in Scotland. The applicant or operator on record is Keltneyburn Hydro Ltd. It is recorded as operational since May 2010. The determining authority is Perth and Kinross.

Site Schematic

UPPER RES. LOWER RES. PENSTOCK TAILRACE GEN. GRID HEAD: ?m Β· POWER: 2.000 MW Β· ? turbines

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKeltneyburn Hydro Ltd
Owner / operatorKeltneyburn Hydro Ltd
Year consented2008
Commissioned / target2010
Locationnr Carse Farm, Aberfeldy, Perthshire, PH15 2JQ, Tayside
RegionScotland
Coordinates56.6139339Β°N, 4.0026703Β°W

Additional published register fields

Registered technologySmall Hydro

πŸ“… Project Timeline

2004-11-22
2008-09-24
2010-05-01