Onshore Wind

Keith Hill

Humbie,, Lothian, EH36 5PN

Keith Hill is a 4.5 MW onshore wind project in Scotland. The applicant or operator on record is Sky Wind Energy. It is recorded as operational since December 2017. The determining authority is Scottish Borders, reference 10/00985/P.…

Operational Β· Since 2017
Project stageOperating
  1. PlanningNov 2010 (completed)
  2. ConsentedApr 2011 (completed)
  3. ConstructionJun 2017 (completed)
  4. OperatingDec 2017 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2018-09-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

4.500 MW
Registered Capacity
2017
Commissioned

πŸ“‹ Project Overview

Keith Hill is a 4.5 MW onshore wind project in Scotland. The applicant or operator on record is Sky Wind Energy. It is recorded as operational since December 2017. The determining authority is Scottish Borders, reference 10/00985/P.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)4.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSky Wind Energy
Owner / operatorSky Wind Energy
Year consented2011
Construction started2017
Commissioned / target2017
LocationHumbie,, Lothian, EH36 5PN
RegionScotland
Coordinates55.8172715Β°N, 2.8254559Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)0.9
No. of Turbines5
Are they re-applying (Old REPD Ref) 4442

πŸ“… Project Timeline

2010-11-15
2011-04-01
2017-06-27