Operational Β· Since 2022
Project stageOperating
  1. PlanningDec 2018 (completed)
  2. ConsentedSep 2019 (completed)
  3. ConstructionDec 2020 (completed)
  4. OperatingApr 2022 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2022-05-12.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2022
Commissioned

πŸ“‹ Project Overview

Keele University is a battery storage project in West Midlands. The applicant or operator on record is Keele University. It is recorded as operational since April 2022. The determining authority is Newcastle-under-Lyme, reference 18/00934/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKeele University
Owner / operatorKeele University
Year consented2019
Construction started2020
Commissioned / target2022
LocationKeele, Newcastle-Under-Lyme,, Staffordshire, ST5 5BG
RegionWest Midlands
Coordinates52.9958701Β°N, 2.2586348Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID7409

πŸ“… Project Timeline

2018-12-20
2019-09-23
2020-12-02
2022-04-29