Battery Storage

Jamesfield Organic Centre - Battery Storage

140 Metres North East Of Jamesfield Organic Centre Newburgh, Cupar, Perth and Kinross, KY14 6EW

Jamesfield Organic Centre - Battery Storage is a 49 MW battery storage project in Scotland. The applicant or operator on record is Harmony Energy Storage. It is recorded as operational since February 2024. The determining authority is Perth and Kinross, reference 22/00832/FLM.…

Operational Β· Since 2024
Project stageOperating
  1. PlanningMay 2022 (completed)
  2. ConsentedSep 2022 (completed)
  3. ConstructionJan 2023 (completed)
  4. OperatingFeb 2024 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2024-03-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.000 MW
Power Capacity
2024
Commissioned

πŸ“‹ Project Overview

Jamesfield Organic Centre - Battery Storage is a 49 MW battery storage project in Scotland. The applicant or operator on record is Harmony Energy Storage. It is recorded as operational since February 2024. The determining authority is Perth and Kinross, reference 22/00832/FLM.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHarmony Energy Storage
Owner / operatorHarmony Energy Storage
Year consented2022
Construction started2023
Commissioned / target2024
Location140 Metres North East Of Jamesfield Organic Centre Newburgh, Cupar, Perth and Kinross, KY14 6EW
RegionScotland
Coordinates56.347677Β°N, 3.2983514Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2022-05-20
2022-09-28
2023-01-01
2024-02-01