π Project Overview
Jamesfield Organic Centre - Battery Storage is a 49 MW battery storage project in Scotland. The applicant or operator on record is Harmony Energy Storage. It is recorded as operational since February 2024. The determining authority is Perth and Kinross, reference 22/00832/FLM.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 49 MW |
| Battery chemistry | Stand-alone Storage |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Harmony Energy Storage |
| Owner / operator | Harmony Energy Storage |
| Year consented | 2022 |
| Construction started | 2023 |
| Commissioned / target | 2024 |
| Location | 140 Metres North East Of Jamesfield Organic Centre Newburgh, Cupar, Perth and Kinross, KY14 6EW |
| Region | Scotland |
| Coordinates | 56.347677Β°N, 3.2983514Β°W |