πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Jamesfield Organic Centre - Battery Storage

140 Metres North East Of Jamesfield Organic Centre Newburgh, Cupar, Perth and Kinross, KY14 6EW

Jamesfield Organic Centre - Battery Storage is a 49 MW battery storage project in Scotland. The applicant or operator on record is Harmony Energy Storage. It is recorded as operational since February 2024. The determining authority is Perth and Kinross, reference 22/00832/FLM.…

Operational Β· Since 2024
49 MW
Power Capacity
2024
Commissioned

πŸ“‹ Project Overview

Jamesfield Organic Centre - Battery Storage is a 49 MW battery storage project in Scotland. The applicant or operator on record is Harmony Energy Storage. It is recorded as operational since February 2024. The determining authority is Perth and Kinross, reference 22/00832/FLM.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHarmony Energy Storage
Owner / operatorHarmony Energy Storage
Year consented2022
Construction started2023
Commissioned / target2024
Location140 Metres North East Of Jamesfield Organic Centre Newburgh, Cupar, Perth and Kinross, KY14 6EW
RegionScotland
Coordinates56.347677Β°N, 3.2983514Β°W

πŸ“… Project Timeline