Isle of Wight Waste Recovery Park

Waste Fuels Plant, Forest Road, Newport, Isle of Wight, PO30 5YS

Isle of Wight Waste Recovery Park is a 3.3 MW other registered technology project in South East. The applicant or operator on record is AmeyCespa. It is recorded as under construction since May 2017. The determining authority is Isle of Wight, reference P/01376/15.…

Under Construction
Project stageUnder construction
  1. PlanningNov 2015 (completed)
  2. ConsentedApr 2016 (completed)
  3. ConstructionMay 2017 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2020-07-27.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

3.300 MW
Registered Capacity

πŸ“‹ Project Overview

Isle of Wight Waste Recovery Park is a 3.3 MW other registered technology project in South East. The applicant or operator on record is AmeyCespa. It is recorded as under construction since May 2017. The determining authority is Isle of Wight, reference P/01376/15.

πŸ”§ Technical Specifications

Capacity (MW)3.300 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAmeyCespa
Owner / operatorAmeyCespa
Year consented2016
Construction started2017
LocationWaste Fuels Plant, Forest Road, Newport, Isle of Wight, PO30 5YS
RegionSouth East
Coordinates50.7049636Β°N, 1.3339459Β°W

Additional published register fields

Registered technologyAdvanced Conversion Technologies

πŸ“… Project Timeline

2015-11-20
2016-04-22
2017-05-15