Invervar Hydro is a 1.2 MW conventional hydro project in Scotland. The applicant or operator on record is Green Highland Renewables (on behalf of North Chesthill Estate). It is recorded as operational since November 2015. The determining authority is Perth and Kinross, reference β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningFeb 2012 (completed)
ConsentedApr 2012 (completed)
ConstructionNov 2014 (completed)
OperatingNov 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-07-12.
Registered planning capacity; not measured generation.
Invervar Hydro is a 1.2 MW conventional hydro project in Scotland. The applicant or operator on record is Green Highland Renewables (on behalf of North Chesthill Estate). It is recorded as operational since November 2015. The determining authority is Perth and Kinross, reference 12/00248/FLL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.200 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Green Highland Renewables (on behalf of North Chesthill Estate)
Owner / operator
Green Highland Renewables (on behalf of North Chesthill Estate)