Inchbean Farm, Treeswoodhead Road - Battery Energy Storage System is a 60 MW battery storage project in Scotland. The applicant or operator on record is RNA Energy Limited. Planning permission has been granted as of June 2025 and it is awaiting construction. The determining autho…

Consented / Approved
Project stageConsented
  1. PlanningNov 2023 (completed)
  2. ConsentedJun 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-07-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

60.000 MW
Power Capacity

πŸ“‹ Project Overview

Inchbean Farm, Treeswoodhead Road - Battery Energy Storage System is a 60 MW battery storage project in Scotland. The applicant or operator on record is RNA Energy Limited. Planning permission has been granted as of June 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004968.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)60.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperRNA Energy Limited
Owner / operatorRNA Energy Limited
Year consented2025
LocationInchbean Farm, Treeswoodhead Road, Shortlees, Kilmarnock, Strathclyde, KA1 5LL
RegionScotland
Coordinates55.5708951Β°N, 4.4810106Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2023-11-11