Ikea Distribution Centre Yorkshire Way Armthorpe Doncaster, South Yorkshire
Ikea Distribution Centre is a 1.7 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is IKEA Properties Investments Ltd. It is recorded as operational since December 2015. The determining authority is Doncaster, reference 14/00366/FUL.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningFeb 2014 (completed)
ConsentedApr 2014 (completed)
ConstructionNov 2014 (completed)
OperatingDec 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-07-27.
Registered planning capacity; not measured generation.
Ikea Distribution Centre is a 1.7 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is IKEA Properties Investments Ltd. It is recorded as operational since December 2015. The determining authority is Doncaster, reference 14/00366/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.700 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
IKEA Properties Investments Ltd
Owner / operator
IKEA Properties Investments Ltd
Year consented
2014
Construction started
2014
Commissioned / target
2015
Location
Ikea Distribution Centre Yorkshire Way Armthorpe Doncaster, South Yorkshire