IBM Limited, IBM Hursley, Winchester, Hampshire, SO21 2JN
IBM Hursley - Battery Storage is a 1.5 MW battery storage project in South East. The applicant or operator on record is IBM UK Limited. Planning permission has been granted as of June 2024 and it is awaiting construction. The determining authority is Winchester, reference 23/0283β¦
Consented / Approved
Project stageConsented
PlanningMar 2024 (completed)
ConsentedJun 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2024-07-08.
Registered planning capacity; not measured generation.
IBM Hursley - Battery Storage is a 1.5 MW battery storage project in South East. The applicant or operator on record is IBM UK Limited. Planning permission has been granted as of June 2024 and it is awaiting construction. The determining authority is Winchester, reference 23/02836/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.500 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
IBM UK Limited
Owner / operator
IBM UK Limited
Year consented
2024
Location
IBM Limited, IBM Hursley, Winchester, Hampshire, SO21 2JN