Battery Storage

Hurst Farm, Mansfield Road - Battery Energy Storage System

Hurst Farm Mansfield Road Tibshelf, Derbyshire, DE55 5NG

Hurst Farm, Mansfield Road - Battery Energy Storage System is a 99.9 MW battery storage project in East Midlands. The applicant or operator on record is Lightsource BP. Planning permission has been granted as of December 2025 and it is awaiting construction. The determining autho…

Consented / Approved
Project stageConsented
  1. PlanningJul 2025 (completed)
  2. ConsentedDec 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-01-06.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

99.900 MW
Power Capacity

πŸ“‹ Project Overview

Hurst Farm, Mansfield Road - Battery Energy Storage System is a 99.9 MW battery storage project in East Midlands. The applicant or operator on record is Lightsource BP. Planning permission has been granted as of December 2025 and it is awaiting construction. The determining authority is Bolsover, reference 25/00302/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)99.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLightsource BP
Owner / operatorLightsource BP
Year consented2025
LocationHurst Farm Mansfield Road Tibshelf, Derbyshire, DE55 5NG
RegionEast Midlands
Coordinates53.1462731Β°N, 1.3282832Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2025-07-28