πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Hunterston

Caledonia Road Lochshore Ind Est, Glengarnock, Beith,, Strathclyde, KA14 3DD

Hunterston is a 5 MW battery storage project in Scotland. The applicant or operator on record is Scottish Enterprise/SSE. The application has been withdrawn or the scheme abandoned. The determining authority is North Ayrshire, reference 08/00576/PPP.…

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningJul 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedMar 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Abandoned.

Official register: July 2026

Recorded status: Abandoned. Source record updated 2019-04-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Power Capacity

πŸ“‹ Project Overview

Hunterston is a 5 MW battery storage project in Scotland. The applicant or operator on record is Scottish Enterprise/SSE. The application has been withdrawn or the scheme abandoned. The determining authority is North Ayrshire, reference 08/00576/PPP.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperScottish Enterprise/SSE
Owner / operatorScottish Enterprise/SSE
Year consented2011
LocationCaledonia Road Lochshore Ind Est, Glengarnock, Beith,, Strathclyde, KA14 3DD
RegionScotland
Coordinates55.7429721Β°N, 4.6759125Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2008-07-15
2011-03-23