Hunters Hall Primary School, Alibon Road, Dagenham, London, RM10 8DE
Hunters Hall Primary School, Alibon Road - Solar Panels is a 0.25 MW solar farm project in London. The applicant or operator on record is Solar Options for Schools Limited. Planning permission has been granted as of July 2024 and it is awaiting construction. The determining authoβ¦
Consented / Approved
Project stageConsented
PlanningMay 2024 (completed)
ConsentedJul 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2024-07-22.
Registered planning capacity; not measured generation.
Hunters Hall Primary School, Alibon Road - Solar Panels is a 0.25 MW solar farm project in London. The applicant or operator on record is Solar Options for Schools Limited. Planning permission has been granted as of July 2024 and it is awaiting construction. The determining authority is Barking and Dagenham, reference 24/00720/PRIPV.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.250 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Solar Options for Schools Limited
Owner / operator
Solar Options for Schools Limited
Year consented
2024
Location