π Project Overview
Hull Biomass Plant (Tansterne power station) is a 22 MW renewable energy project in Yorkshire and Humber. The applicant or operator on record is Solar 21. It is recorded as operational since February 2018. The determining authority is East Riding of Yorkshire, reference 15/03102/STREM.
π§ Technical Specifications
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Solar 21 |
| Owner / operator | Solar 21 |
| Year consented | 2016 |
| Construction started | 2016 |
| Commissioned / target | 2018 |
| Location | Land at Tansterne Grange, Tansterne Lane, East Riding Of Yorkshire, Humberside, HU11 4 RD |
| Region | Yorkshire and Humber |
| Coordinates | 53.8190455Β°N, 0.1464717Β°W |