πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Hopsrig Wind Farm

7.5Km NW of Langholm, Westerkirk, Langholm, Dumfries and Galloway, DG13 0A

Hopsrig Wind Farm is a 42 MW onshore wind project in Scotland. The applicant or operator on record is Buccleuch Estate/ 2020 Renewables. The scheme is currently in the planning system, submitted March 2017. The determining authority is Dumfries and Galloway, reference 17/0415/FUL…

Revised
Project stageSuperseded by a new application
  1. PlanningMar 2017 (completed)
  2. Superseded by a new application (project stopped here)
  3. ConsentedJan 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2022-07-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

42.000 MW
Registered Capacity

πŸ“‹ Project Overview

Hopsrig Wind Farm is a 42 MW onshore wind project in Scotland. The applicant or operator on record is Buccleuch Estate/ 2020 Renewables. The scheme is currently in the planning system, submitted March 2017. The determining authority is Dumfries and Galloway, reference 17/0415/FUL.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)42.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBuccleuch Estate/ 2020 Renewables
Owner / operatorBuccleuch Estate/ 2020 Renewables
Year consented2019
Location7.5Km NW of Langholm, Westerkirk, Langholm, Dumfries and Galloway, DG13 0A
RegionScotland
Coordinates55.1870151Β°N, 3.140457Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)3.5
No. of Turbines12
Height of Turbines (m)140
Are they re-applying (New REPD Ref)11065 & 11066

πŸ“… Project Timeline

2017-03-02
2019-01-28