Land North And South Of 1 Whinhouse, Hoprigshiels, Cockburnspath, Scottish Borders, Borders
Hoprigshiels Community Wind Farm is a 6.9 MW onshore wind project in Scotland. The applicant or operator on record is Private Developer. It is recorded as operational since March 2017. The determining authority is Scottish Borders, reference 11/00664/FUL.β¦
OperationalΒ· Since 2017
Project stageOperating
PlanningJun 2011 (completed)
ConsentedNov 2014 (completed)
ConstructionJan 2016 (completed)
OperatingMar 2017 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-07-14.
Registered planning capacity; not measured generation.
Hoprigshiels Community Wind Farm is a 6.9 MW onshore wind project in Scotland. The applicant or operator on record is Private Developer. It is recorded as operational since March 2017. The determining authority is Scottish Borders, reference 11/00664/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
6.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Private Developer
Owner / operator
Private Developer
Year consented
2014
Construction started
2016
Commissioned / target
2017
Location
Land North And South Of 1 Whinhouse, Hoprigshiels, Cockburnspath, Scottish Borders, Borders