Hodgetts Lane, Berkswell - Electricity Storage Facility

E/O Hodgetts Lane, Berkswell, Solihull, West Midlands, CV7 7DF

Hodgetts Lane, Berkswell - Electricity Storage Facility is a 49.9 MW battery storage project in West Midlands. The applicant or operator on record is Coventry Energy Storage Limited. The scheme is currently in the planning system, submitted July 2024. The determining authority is…

In Planning
Project stageIn planning
  1. PlanningJul 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Application Submitted.

Official register: July 2026

Recorded status: Planning Application Submitted. Source record updated 2025-02-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Power Capacity

πŸ“‹ Project Overview

Hodgetts Lane, Berkswell - Electricity Storage Facility is a 49.9 MW battery storage project in West Midlands. The applicant or operator on record is Coventry Energy Storage Limited. The scheme is currently in the planning system, submitted July 2024. The determining authority is Solihull, reference PL/2024/01261/PPFL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCoventry Energy Storage Limited
Owner / operatorCoventry Energy Storage Limited
LocationE/O Hodgetts Lane, Berkswell, Solihull, West Midlands, CV7 7DF
RegionWest Midlands
Coordinates52.386266Β°N, 1.610608Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (Old REPD Ref) 15230

πŸ“… Project Timeline

2024-07-02