Bioenergy / Waste

Himley Wood Landfill Site

Himley Wood Landfill Site Himley Road Himley Staffordshire, Staffordshire

Himley Wood Landfill Site is a 4.4 MW bioenergy / waste project in West Midlands. The applicant or operator on record is Biogeneration / Biffa. It is recorded as operational since August 1996. The determining authority is South Staffordshire.…

Operational Β· Since 1996
Project stageOperating
  1. PlanningNov 1992 (completed)
  2. ConsentedMar 1995 (completed)
  3. Construction (completed)
  4. OperatingAug 1996 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2013-10-08.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

4.400 MW
Registered Capacity
1996
Commissioned

πŸ“‹ Project Overview

Himley Wood Landfill Site is a 4.4 MW bioenergy / waste project in West Midlands. The applicant or operator on record is Biogeneration / Biffa. It is recorded as operational since August 1996. The determining authority is South Staffordshire.

πŸ”§ Technical Specifications

Capacity (MW)4.400 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBiogeneration / Biffa
Owner / operatorBiogeneration / Biffa
Year consented1995
Commissioned / target1996
LocationHimley Wood Landfill Site Himley Road Himley Staffordshire, Staffordshire
RegionWest Midlands
Coordinates52.5158892Β°N, 2.1502645Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1992-11-26
1995-03-24
1996-08-01