Hill Farm, Hill Farm Lane, Duns Tew, Bicester, Oxfordshire, Oxfordshire, OX25 6JJ
Hill Farm is a 5 MW solar farm project in South East. The applicant or operator on record is NESF (formerly Earthworm). It is recorded as operational since March 2017. The determining authority is Cherwell, reference 15/00570/F.β¦
OperationalΒ· Since 2017
Project stageOperating
PlanningMar 2015 (completed)
ConsentedOct 2015 (completed)
ConstructionFeb 2017 (completed)
OperatingMar 2017 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-05-03.
Registered planning capacity; not measured generation.
Hill Farm is a 5 MW solar farm project in South East. The applicant or operator on record is NESF (formerly Earthworm). It is recorded as operational since March 2017. The determining authority is Cherwell, reference 15/00570/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
NESF (formerly Earthworm)
Owner / operator
NESF (formerly Earthworm)
Year consented
2015
Construction started
2017
Commissioned / target
2017
Location
Hill Farm, Hill Farm Lane, Duns Tew, Bicester, Oxfordshire, Oxfordshire, OX25 6JJ