πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Highflat Battery Energy Storage

Land At, Cairnmuir Road, East Kilbride, Glasgow, Strathclyde, Lanarkshire, G74 4GY

Highflat Battery Energy Storage is a 19.9 MW battery storage project in Scotland. The applicant or operator on record is Highflat Energy Storage. The application has been withdrawn or the scheme abandoned. The determining authority is South Lanarkshire, reference P/18/0528.…

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningApr 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Application Withdrawn.

Official register: July 2026

Recorded status: Planning Application Withdrawn. Source record updated 2018-11-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

19.900 MW
Power Capacity

πŸ“‹ Project Overview

Highflat Battery Energy Storage is a 19.9 MW battery storage project in Scotland. The applicant or operator on record is Highflat Energy Storage. The application has been withdrawn or the scheme abandoned. The determining authority is South Lanarkshire, reference P/18/0528.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)19.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHighflat Energy Storage
Owner / operatorHighflat Energy Storage
LocationLand At, Cairnmuir Road, East Kilbride, Glasgow, Strathclyde, Lanarkshire, G74 4GY
RegionScotland
Coordinates55.7916272Β°N, 4.19525Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2018-04-26