Higher Hill Farm (extension) is a 1.5 MW solar farm project in South West. The applicant or operator on record is British Solar Renewables. It is recorded as operational since May 2016. The determining authority is Somerset, reference 2014/0646/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 2 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | British Solar Renewables |
| Owner / operator | British Solar Renewables |
| Year consented | 2014 |
| Construction started | 2015 |
| Commissioned / target | 2016 |
| Location | Land At Higher Hill Farm, Butleigh Hill, Butleigh, Glastonbury, Somerset, Somerset, BA6 8TW |
| Region | South West |