πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Higher Hill Farm

Butleigh, Glastonbury, Somerset, Somerset

Higher Hill Farm is a 5 MW solar farm project in South West. The applicant or operator on record is Solar Power Generation. It is recorded as operational since September 2011. The determining authority is Somerset, reference 2011/0688.…

Operational Β· Since 2011
Project stageOperating
  1. PlanningMar 2011 (completed)
  2. ConsentedJun 2011 (completed)
  3. Construction (completed)
  4. OperatingSep 2011 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2012-10-25.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity
2011
Commissioned

πŸ“‹ Project Overview

Higher Hill Farm is a 5 MW solar farm project in South West. The applicant or operator on record is Solar Power Generation. It is recorded as operational since September 2011. The determining authority is Somerset, reference 2011/0688.

Site Schematic

SUBSTATION ? ha Β· 5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSolar Power Generation
Owner / operatorSolar Power Generation
Year consented2011
Commissioned / target2011
LocationButleigh, Glastonbury, Somerset, Somerset
RegionSouth West
Coordinates51.076326Β°N, 2.6891541Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)107000

πŸ“… Project Timeline

2011-03-29
2011-06-24
2011-09-26