Adj Former High Marnham Power Station High Marnham, Nottinghamshire, NG23 6SH
High Marnham - Solar Photovoltaic Farm is a 42.7 MW solar farm project in East Midlands. The applicant or operator on record is J G Pears Property Limited. Planning permission has been granted as of January 2023 and it is awaiting construction. The determining authority is Bassetβ¦
Consented / Approved
Project stageConsented
PlanningMay 2022 (completed)
ConsentedJan 2023 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2022-06-06.
Registered planning capacity; not measured generation.
High Marnham - Solar Photovoltaic Farm is a 42.7 MW solar farm project in East Midlands. The applicant or operator on record is J G Pears Property Limited. Planning permission has been granted as of January 2023 and it is awaiting construction. The determining authority is Bassetlaw, reference 22/00707/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
42.700 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
J G Pears Property Limited
Owner / operator
J G Pears Property Limited
Year consented
2023
Location