Battery Storage

HHT Battery Energy Storage System in Randalstown

Lands Approximately 285m South East of No 52 Moneynick Road, Randalstown, Co. Antrim, BT41 3HW

HHT Battery Energy Storage System in Randalstown is a 1 MW battery storage project in Northern Ireland. The applicant or operator on record is HHT Renewables Ltd. Planning permission has been granted as of August 2024 and it is awaiting construction. The determining authority is …

Consented / Approved
Project stageConsented
  1. PlanningNov 2023 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-08-27.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.000 MW
Power Capacity

πŸ“‹ Project Overview

HHT Battery Energy Storage System in Randalstown is a 1 MW battery storage project in Northern Ireland. The applicant or operator on record is HHT Renewables Ltd. Planning permission has been granted as of August 2024 and it is awaiting construction. The determining authority is Antrim and Newtownabbey, reference LA03/2023/0901/F.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHHT Renewables Ltd
Owner / operatorHHT Renewables Ltd
Year consented2024
LocationLands Approximately 285m South East of No 52 Moneynick Road, Randalstown, Co. Antrim, BT41 3HW
RegionNorthern Ireland
Coordinates54.7432841Β°N, 6.3409123Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2023-11-28
2024-08-01