Pondpool Lane, Helland, North Curry, Taunton, Somerset, TA3 6DU
Helland Meads is a 1.2 MW solar farm project in South West. The applicant or operator on record is Private Developer. It is recorded as operational since November 2014. The determining authority is Somerset, reference 24/14/0020.β¦
OperationalΒ· Since 2014
Project stageOperating
PlanningApr 2014 (completed)
ConsentedJun 2014 (completed)
ConstructionSep 2014 (completed)
OperatingNov 2014 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-07-27.
Registered planning capacity; not measured generation.
Helland Meads is a 1.2 MW solar farm project in South West. The applicant or operator on record is Private Developer. It is recorded as operational since November 2014. The determining authority is Somerset, reference 24/14/0020.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.200 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Private Developer
Owner / operator
Private Developer
Year consented
2014
Construction started
2014
Commissioned / target
2014
Location
Pondpool Lane, Helland, North Curry, Taunton, Somerset, TA3 6DU