Solar Farm

Hayford Farm

Westbury, Shrewsbury, Shropshire, Shropshire, SY5 9PF

Hayford Farm is a 8.9 MW solar farm project in West Midlands. The applicant or operator on record is WS Systems Ltd. It is recorded as operational since September 2014. The determining authority is Shropshire, reference 12/03725/FUL.…

Operational Β· Since 2014
Project stageOperating
  1. PlanningSep 2012 (completed)
  2. ConsentedDec 2012 (completed)
  3. ConstructionJul 2014 (completed)
  4. OperatingSep 2014 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2015-09-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

8.900 MW
Registered Capacity
2014
Commissioned

πŸ“‹ Project Overview

Hayford Farm is a 8.9 MW solar farm project in West Midlands. The applicant or operator on record is WS Systems Ltd. It is recorded as operational since September 2014. The determining authority is Shropshire, reference 12/03725/FUL.

Site Schematic

SUBSTATION ? ha Β· 8.9 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)8.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWS Systems Ltd
Owner / operatorWS Systems Ltd
Year consented2012
Construction started2014
Commissioned / target2014
LocationWestbury, Shrewsbury, Shropshire, Shropshire, SY5 9PF
RegionWest Midlands
Coordinates52.6894803Β°N, 2.9445358Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround

πŸ“… Project Timeline

2012-09-10
2012-12-20
2014-07-01
2014-09-10