Hatton Solar Farm is a 49.9 MW solar farm project in East Midlands. The applicant or operator on record is Push Energy. Planning permission has been granted as of December 2025 and it is awaiting construction. The determining authority is East Lindsey, reference S/079/01078/22.β¦
Consented / Approved
Project stageConsented
PlanningJun 2022 (completed)
ConsentedDec 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Appeal Granted.
Official register: July 2026
Recorded status: Appeal Granted. Source record updated 2026-01-26.
Registered planning capacity; not measured generation.
Hatton Solar Farm is a 49.9 MW solar farm project in East Midlands. The applicant or operator on record is Push Energy. Planning permission has been granted as of December 2025 and it is awaiting construction. The determining authority is East Lindsey, reference S/079/01078/22.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.