Battery Storage

Harrington Franklin, Richborough Energy Park - Battery Storage

Part Of Former Richborough Power Station Ramsgate Road, Kent, CT13 9DE

Harrington Franklin, Richborough Energy Park - Battery Storage is a 49.9 MW battery storage project in South East. The applicant or operator on record is EDP Renewables. It is recorded as under construction since December 2024. The determining authority is Dover, reference 22/007…

Under Construction
Project stageUnder construction
  1. PlanningJun 2022 (completed)
  2. ConsentedDec 2022 (completed)
  3. ConstructionDec 2024 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2025-06-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Power Capacity

πŸ“‹ Project Overview

Harrington Franklin, Richborough Energy Park - Battery Storage is a 49.9 MW battery storage project in South East. The applicant or operator on record is EDP Renewables. It is recorded as under construction since December 2024. The determining authority is Dover, reference 22/00705.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEDP Renewables
Owner / operatorEDP Renewables
Year consented2022
Construction started2024
LocationPart Of Former Richborough Power Station Ramsgate Road, Kent, CT13 9DE
RegionSouth East
Coordinates51.3061245Β°N, 1.3485739Β°E

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2022-06-01
2022-12-06
2024-12-01