Harburnhead Wind Farm is a 51.7 MW onshore wind project in Scotland. The applicant or operator on record is Gresham House. It is recorded as operational since December 2016. The determining authority is Scottish Government (S36).
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 52 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Gresham House |
| Owner / operator | Gresham House |
| Year consented | 2014 |
| Construction started | 2016 |
| Commissioned / target | 2016 |
| Location | West Calder, West Lothian, Lothian |
| Region | Scotland |
| Coordinates | 55.8086812Β°N, 3.5321722Β°W |