πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Hapton Valley Transfer Station, Accrington Road - Combined Heat And Power

Hapton Valley Transfer Station, Hapton Valley Estate, Accrington Road, Burnley, Lancashire, BB11 5QG

Hapton Valley Transfer Station, Accrington Road - Combined Heat And Power is a bioenergy / waste project in North West. The applicant or operator on record is ETGAS Burnley Limited. Planning permission has been granted as of November 2023 and it is awaiting construction. The dete…

Consented / Approved
Project stageConsented
  1. PlanningAug 2023 (completed)
  2. ConsentedNov 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2023-11-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

πŸ“‹ Project Overview

Hapton Valley Transfer Station, Accrington Road - Combined Heat And Power is a bioenergy / waste project in North West. The applicant or operator on record is ETGAS Burnley Limited. Planning permission has been granted as of November 2023 and it is awaiting construction. The determining authority is Burnley, reference LCC/2023/0024.

πŸ”§ Technical Specifications

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperETGAS Burnley Limited
Owner / operatorETGAS Burnley Limited
Year consented2023
LocationHapton Valley Transfer Station, Hapton Valley Estate, Accrington Road, Burnley, Lancashire, BB11 5QG
RegionNorth West
Coordinates53.7782265Β°N, 2.2911343Β°W

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

2023-08-10
2023-11-08