πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Handley Park

Handley Park Farm, Handley Park, Towcester, Northamptonshire

Handley Park is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Haymaker Energy. It is recorded as operational since March 2016. The determining authority is West Northamptonshire, reference S/2014/1522/MAF.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningAug 2014 (completed)
  2. ConsentedSep 2015 (completed)
  3. ConstructionMay 2016 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-06-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Handley Park is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Haymaker Energy. It is recorded as operational since March 2016. The determining authority is West Northamptonshire, reference S/2014/1522/MAF.

Site Schematic

SUBSTATION ? ha Β· 5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHaymaker Energy
Owner / operatorHaymaker Energy
Year consented2015
Construction started2016
Commissioned / target2016
LocationHandley Park Farm, Handley Park, Towcester, Northamptonshire
RegionEast Midlands
Coordinates52.1079454Β°N, 1.0207395Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Are they re-applying (Old REPD Ref) 1993
Solar Site Area (sqm)255000

πŸ“… Project Timeline

2014-08-21
2015-09-09
2016-05-01
2016-03-24