290 Metres E/O Hams Hall Electricity Sub Station, Hams Lane, Lea Marston, Sutton Coldfield, West Midlands, B76 0BY
Hams Hall, Hams Lane - Battery Energy Storage System is a 98 MW battery storage project in West Midlands. The applicant or operator on record is Eon UK Plc. Planning permission has been granted as of October 2025 and it is awaiting construction. The determining authority is Northβ¦
Consented / Approved
Project stageConsented
PlanningMay 2025 (completed)
ConsentedOct 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-12-02.
Registered planning capacity; not measured generation.
Hams Hall, Hams Lane - Battery Energy Storage System is a 98 MW battery storage project in West Midlands. The applicant or operator on record is Eon UK Plc. Planning permission has been granted as of October 2025 and it is awaiting construction. The determining authority is North Warwickshire, reference PAP/2025/0227.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
98.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Eon UK Plc
Owner / operator
Eon UK Plc
Year consented
2025
Location
290 Metres E/O Hams Hall Electricity Sub Station, Hams Lane, Lea Marston, Sutton Coldfield, West Midlands, B76 0BY