Land off the B397, Netley Abbey, Hound, Southampton, Hampshire, Hampshire, SO31 5FT
Hamble Lane Battery Energy Storage is a 6 MW battery storage project in South East. The applicant or operator on record is Balanced Grid Solutions. Planning permission has been granted as of November 2019 and it is awaiting construction. The determining authority is Eastleigh, reβ¦
Consented / Approved
Project stageConsented
PlanningApr 2019 (completed)
ConsentedNov 2019 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2020-01-31.
Registered planning capacity; not measured generation.
Hamble Lane Battery Energy Storage is a 6 MW battery storage project in South East. The applicant or operator on record is Balanced Grid Solutions. Planning permission has been granted as of November 2019 and it is awaiting construction. The determining authority is Eastleigh, reference F/19/85302.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
6.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Balanced Grid Solutions
Owner / operator
Balanced Grid Solutions
Year consented
2019
Location
Land off the B397, Netley Abbey, Hound, Southampton, Hampshire, Hampshire, SO31 5FT