Hall Farm, Main Street, Newbold Verdon, LEICESTER, LE9 9NL, Leicestershire
Hall Farm Solar Farm (Newbold Verdon) is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Push Energy/ NextEnergy Solar Fund (NESF). It is recorded as operational since December 2015. The determining authority is Hinckley and Bosworth, reference β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningJul 2014 (completed)
ConsentedJun 2015 (completed)
ConstructionSep 2015 (completed)
OperatingDec 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-07-18.
Registered planning capacity; not measured generation.
Hall Farm Solar Farm (Newbold Verdon) is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Push Energy/ NextEnergy Solar Fund (NESF). It is recorded as operational since December 2015. The determining authority is Hinckley and Bosworth, reference 14/00660/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Push Energy/ NextEnergy Solar Fund (NESF)
Owner / operator
Push Energy/ NextEnergy Solar Fund (NESF)
Year consented
2015
Construction started
2015
Commissioned / target
2015
Location
Hall Farm, Main Street, Newbold Verdon, LEICESTER, LE9 9NL, Leicestershire