Land North West of Sileby Road, Barrow, Leicestershire, Leicestershire, LE12 8GB
Gypsom Solar Farm is a 5 MW solar farm project in East Midlands. The applicant or operator on record is BE Renewables. It is recorded as operational since March 2017. The determining authority is Charnwood, reference P/14/2359/2.β¦
OperationalΒ· Since 2017
Project stageOperating
PlanningJan 2015 (completed)
ConsentedSep 2015 (completed)
ConstructionJan 2017 (completed)
OperatingMar 2017 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-10-31.
Registered planning capacity; not measured generation.
Gypsom Solar Farm is a 5 MW solar farm project in East Midlands. The applicant or operator on record is BE Renewables. It is recorded as operational since March 2017. The determining authority is Charnwood, reference P/14/2359/2.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
BE Renewables
Owner / operator
BE Renewables
Year consented
2015
Construction started
2017
Commissioned / target
2017
Location
Land North West of Sileby Road, Barrow, Leicestershire, Leicestershire, LE12 8GB