Gynsill Lane, Leicester Road - Micro Energy Storage is a 0.2 MW battery storage project in East Midlands. The applicant or operator on record is AMP Clean Energy. Planning permission has been granted as of May 2026 and it is awaiting construction. The determining authority is Cha…

Consented / Approved
Project stageConsented
  1. PlanningMar 2026 (completed)
  2. ConsentedMay 2026 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated date not supplied.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.200 MW
Power Capacity

πŸ“‹ Project Overview

Gynsill Lane, Leicester Road - Micro Energy Storage is a 0.2 MW battery storage project in East Midlands. The applicant or operator on record is AMP Clean Energy. Planning permission has been granted as of May 2026 and it is awaiting construction. The determining authority is Charnwood, reference P/26/0633/2.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.200 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAMP Clean Energy
Owner / operatorAMP Clean Energy
Year consented2026
LocationGynsill Lane meets Leicester Road Anstey, Leicestershire, LE7 7AP
RegionEast Midlands
Coordinates52.6662592Β°N, 1.1779762Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2026-03-31
2026-05-26