Grove Solar Park, Land west of A3057 (Romsey Road), Romsey, Hampshire, SO51 9LH
Grove Solar Park (Phase 2) is a 11 MW solar farm project in South East. The applicant or operator on record is Solar Century. It is recorded as operational since March 2016. The determining authority is Test Valley, reference 14/01826/FULLS.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningJul 2014 (completed)
ConsentedSep 2015 (completed)
ConstructionJan 2016 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-01-16.
Registered planning capacity; not measured generation.
Grove Solar Park (Phase 2) is a 11 MW solar farm project in South East. The applicant or operator on record is Solar Century. It is recorded as operational since March 2016. The determining authority is Test Valley, reference 14/01826/FULLS.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
11.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Solar Century
Owner / operator
Solar Century
Year consented
2015
Construction started
2016
Commissioned / target
2016
Location
Grove Solar Park, Land west of A3057 (Romsey Road), Romsey, Hampshire, SO51 9LH