πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Gronan

Golandun Dolan, Killeter, Castlederg, Co. Tyrone

Gronan is a 9.2 MW onshore wind project in Northern Ireland. The applicant or operator on record is DW Consultancy. Planning permission has been granted as of December 2018 and it is awaiting construction. The determining authority is Derry City and Strabane, reference J/2007/066…

Consented / Approved
Project stageConsented
  1. PlanningOct 2007 (completed)
  2. ConsentedDec 2018 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2020-02-27.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

9.200 MW
Registered Capacity

πŸ“‹ Project Overview

Gronan is a 9.2 MW onshore wind project in Northern Ireland. The applicant or operator on record is DW Consultancy. Planning permission has been granted as of December 2018 and it is awaiting construction. The determining authority is Derry City and Strabane, reference J/2007/0667/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)9.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperDW Consultancy
Owner / operatorDW Consultancy
Year consented2018
LocationGolandun Dolan, Killeter, Castlederg, Co. Tyrone
RegionNorthern Ireland
Coordinates54.6676681Β°N, 7.6735236Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.3
No. of Turbines4

πŸ“… Project Timeline

2007-10-02
2018-12-20