South of Gretna 400kv Substation, Gretna, Dumfries and Galloway, DG16 5HR
Gretna Green Battery Storage is a 456 MW battery storage project in Scotland. The applicant or operator on record is Gresham House Devco Pipeline. Planning permission has been granted as of March 2025 and it is awaiting construction. The determining authority is Scottish Governmeβ¦
Consented / Approved
Project stageConsented
PlanningApr 2024 (completed)
ConsentedMar 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-05-06.
Registered planning capacity; not measured generation.
Gretna Green Battery Storage is a 456 MW battery storage project in Scotland. The applicant or operator on record is Gresham House Devco Pipeline. Planning permission has been granted as of March 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004986.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
456.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Gresham House Devco Pipeline
Owner / operator
Gresham House Devco Pipeline
Year consented
2025
Location
South of Gretna 400kv Substation, Gretna, Dumfries and Galloway, DG16 5HR