Field South East Of Sub Statio, Station Road, Grendon, Wellingborough, Northampton, Northamptonshire, Northamptonshire, NN7 1JW
Grendon Storage is a 49.9 MW battery storage project in East Midlands. The applicant or operator on record is Statera Energy / Grendon Storage. The planning permission has expired. The determining authority is North Northamptonshire, reference WP/17/00602/FUL.β¦
Expired
Project stageConsent lapsed
PlanningSep 2017 (completed)
ConsentedNov 2017 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2020-08-21.
Registered planning capacity; not measured generation.
Grendon Storage is a 49.9 MW battery storage project in East Midlands. The applicant or operator on record is Statera Energy / Grendon Storage. The planning permission has expired. The determining authority is North Northamptonshire, reference WP/17/00602/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Statera Energy / Grendon Storage
Owner / operator
Statera Energy / Grendon Storage
Year consented
2017
Location