N/O Green Man Road, Navenby, Lincoln, Lincolnshire, LN5 0JY
Green Man Road, Navenby - Battery Storage is a 400 MW battery storage project in East Midlands. The applicant or operator on record is Windel Energy / Canadian Solar. The scheme is currently in the planning system, submitted May 2025. The determining authority is North Kesteven, β¦
In Planning
Project stageIn planning
PlanningMay 2025 (current stage)
Consented (not yet reached)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Application Submitted.
Official register: July 2026
Recorded status: Planning Application Submitted. Source record updated 2025-06-13.
Registered planning capacity; not measured generation.
Green Man Road, Navenby - Battery Storage is a 400 MW battery storage project in East Midlands. The applicant or operator on record is Windel Energy / Canadian Solar. The scheme is currently in the planning system, submitted May 2025. The determining authority is North Kesteven, reference 25/0491/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
400.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Windel Energy / Canadian Solar
Owner / operator
Windel Energy / Canadian Solar
Location
N/O Green Man Road, Navenby, Lincoln, Lincolnshire, LN5 0JY