South Of Green Lane And West Of Cliff Lane, Gonerby Moor, Lincolnshire, NG32 2AD
Green Lane & Cliff Lane, Gonerby Moor - Solar Farm is a 23 MW solar farm project in East Midlands. The applicant or operator on record is Lightsource BP. Planning permission has been granted as of January 2024 and it is awaiting construction. The determining authority is South Keβ¦
Consented / Approved
Project stageConsented
PlanningOct 2023 (completed)
ConsentedJan 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-07-28.
Registered planning capacity; not measured generation.
Green Lane & Cliff Lane, Gonerby Moor - Solar Farm is a 23 MW solar farm project in East Midlands. The applicant or operator on record is Lightsource BP. Planning permission has been granted as of January 2024 and it is awaiting construction. The determining authority is South Kesteven, reference S23/1934.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
23.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Lightsource BP
Owner / operator
Lightsource BP
Year consented
2024
Location
South Of Green Lane And West Of Cliff Lane, Gonerby Moor, Lincolnshire, NG32 2AD