Solar Farm

Great Wheatley Road - Solar Farm

W/O Great Wheatley Farm, Great Wheatley Road, Rayleigh, Essex, SS6 7AL

Great Wheatley Road - Solar Farm is a 30 MW solar farm project in Eastern. The applicant or operator on record is Aura Power Solar UK Limited. It is recorded as under construction since January 2026. The determining authority is Rochford, reference 22/00175/FUL.…

Under Construction
Project stageUnder construction
  1. PlanningMar 2022 (completed)
  2. ConsentedMar 2024 (completed)
  3. ConstructionJan 2026 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2026-06-17.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

30.000 MW
Registered Capacity

πŸ“‹ Project Overview

Great Wheatley Road - Solar Farm is a 30 MW solar farm project in Eastern. The applicant or operator on record is Aura Power Solar UK Limited. It is recorded as under construction since January 2026. The determining authority is Rochford, reference 22/00175/FUL.

Site Schematic

SUBSTATION ? ha Β· 30 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)30.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAura Power Solar UK Limited
Owner / operatorAura Power Solar UK Limited
Year consented2024
Construction started2026
LocationW/O Great Wheatley Farm, Great Wheatley Road, Rayleigh, Essex, SS6 7AL
RegionEastern
Coordinates51.581305Β°N, 0.5975642Β°E

Additional published register fields

Registered technologySolar Photovoltaics
CfD Allocation RoundAR6
CfD Capacity (MW)30
Mounting Type for SolarGround
Solar Site Area (sqm)452000

πŸ“… Project Timeline

2022-03-17
2024-03-11
2026-01-01