Great Oak Energy Hub is a 400 MW battery storage project in South East. The applicant or operator on record is Clearstone Energy Limited. Planning permission has been granted as of March 2025 and it is awaiting construction. The determining authority is Horsham, reference DC/24/1289.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 400 MW |
| Battery chemistry | Stand-alone Storage |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Clearstone Energy Limited |
| Owner / operator | Clearstone Energy Limited |
| Year consented | 2025 |
| Location | Adj To Shipley Road, Southwater, Horsham, West Sussex, RH13 9BQ |
| Region | South East |
| Coordinates | 51.0090162Β°N, 0.3568837Β°W |