πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Granox Biogas Plant

Desoto Road, Widnes, Cheshire, WA8 0PB

Granox Biogas Plant is a 5 MW bioenergy / waste project in North West. The applicant or operator on record is ReFood UK. It is recorded as operational since June 2014. The determining authority is Halton, reference 12/00156/FULEIA.…

Operational Β· Since 2014
Project stageOperating
  1. PlanningMar 2012 (completed)
  2. ConsentedOct 2012 (completed)
  3. ConstructionJan 2013 (completed)
  4. OperatingJun 2014 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-08-11.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity
2014
Commissioned

πŸ“‹ Project Overview

Granox Biogas Plant is a 5 MW bioenergy / waste project in North West. The applicant or operator on record is ReFood UK. It is recorded as operational since June 2014. The determining authority is Halton, reference 12/00156/FULEIA.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperReFood UK
Owner / operatorReFood UK
Year consented2012
Construction started2013
Commissioned / target2014
LocationDesoto Road, Widnes, Cheshire, WA8 0PB
RegionNorth West
Coordinates53.3524714Β°N, 2.7467308Β°W

Additional published register fields

Registered technologyAnaerobic Digestion

πŸ“… Project Timeline

2012-03-21
2012-10-19
2013-01-01
2014-06-18