Verge Off Grafton Street, End Of Dunsby Road, Redmoor, Milton Keynes, Buckinghamshire, MK6 4AD
Grafton Street, End Of Dunsby Road - Micro Energy Storage Facility is a 0.2 MW battery storage project in South East. The applicant or operator on record is AMP Clean Energy. Planning permission has been granted as of January 2025 and it is awaiting construction. The determining β¦
Consented / Approved
Project stageConsented
PlanningDec 2024 (completed)
ConsentedJan 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-02-10.
Registered planning capacity; not measured generation.
Grafton Street, End Of Dunsby Road - Micro Energy Storage Facility is a 0.2 MW battery storage project in South East. The applicant or operator on record is AMP Clean Energy. Planning permission has been granted as of January 2025 and it is awaiting construction. The determining authority is Milton Keynes, reference PLN/2024/2497.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.200 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
AMP Clean Energy
Owner / operator
AMP Clean Energy
Year consented
2025
Location
Verge Off Grafton Street, End Of Dunsby Road, Redmoor, Milton Keynes, Buckinghamshire, MK6 4AD