Operational Β· Since 1996
Project stageOperating
  1. PlanningSep 1994 (completed)
  2. ConsentedDec 1994 (completed)
  3. Construction (completed)
  4. OperatingMay 1996 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2003-03-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.600 MW
Registered Capacity
1996
Commissioned

πŸ“‹ Project Overview

Gowy Landfill Site is a 1.6 MW bioenergy / waste project in North West. The applicant or operator on record is Waste Recycling Group. It is recorded as operational since May 1996. The determining authority is Cheshire West and Chester.

πŸ”§ Technical Specifications

Capacity (MW)1.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWaste Recycling Group
Owner / operatorWaste Recycling Group
Year consented1994
Commissioned / target1996
LocationGowy Landfill Site Ince Lane Wimbolds Trafford near Chester Cheshire, Cheshire
RegionNorth West
Coordinates53.2376247Β°N, 2.8315123Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1994-09-06
1994-12-13
1996-05-01